marathon® burner courier 01/2019

Premium marathon ® combustion systems in worldwide operation… Installation example Netherlands Project steps The professional commissioning of the 14 marathon ® DUObloc gas burners by experienced specialists was completed in November 2018. Pure energy. Reliable. Efficient. Clean. Page 5 marathon ® burner courier Boiler house Delivery of the DUObloc burner Installation of in Den Haag marathon ® burner with fan and motor combustion air fan Assembly of burner 1 Existing boiler Transport of the burner Positioning of the fan on double flame tube boiler Babcock Euronox with the crane above the boiler Control cabinet with 2 x marathon ® Boiler/burner plant frequency converter M 10003.4 ARZ in Leiden Retrofitting 14 LOW-NO x marathon ® GAS BURNER We thank the competent serviceteam of K.K. Brandertechniek .