Premium marathon
®
combustion systems in world wide operation…
Example of a power plant in Poland
Project steps
Pure Energy.
Reliable.
Efficient.
Clean.
Page 3
marathon
®
burner courier
March 2011
Pressure testing of the boilers of Bosch
Industriekessel GmbH in the factory
Gunzenhausen
April 2011
Ship loading of the boiler/burner units.
By cargo ship traveling from
Gunzenhausen to Cigacicach on the
Oder and further on the road as heavy
transport for delivery and installation in
the boiler house Zielona Gora.
Precision performance: Handling of the
6 boiler/burner units with a special
crane through the roof of the boiler
house.
June 2012
Successful
commissioning
by
experienced and first-class specialists:
The competent Team of Loos Poland
and dreizler
®
.